barexams.org
Menu
PULSE LIVE
Sample evaluation · Solano v. Varkell Roofing LLC

A real evaluation, unedited.

Below is exactly what you get. We wrote a deliberately mid-quality answer to one of our NextGen-style performance tasks — the kind that spots the big issue but goes thin on remedies — and ran it through the grader, unedited. It scored 6.5/12. (A strong answer to the same task scores 11–12; a weak one scores 3–4. The grader can tell the difference — that's the point.)

This is a passing-level answer on the notice/waiver issues but it never engages the substantial-completion analysis that the point sheet treats as the case's central factual dispute, which caps its overall strength.

One change for your next attempt

Highest-leverage fix: Add explicit Danvers-based analysis comparing Varkell's best argument (main-house roof water-tight and in use) against Solano's better facts (unstarted garage section, missing gutters/drip edge, no final inspection) to reach a reasoned conclusion on whether substantial completion has occurred — this is the single gap costing you the most credit.

Issue 1
Applicability of the Act; violations of §§ 24-410(a) and (b)
Rule 3/4 · Analysis 3/4
Issue 2
Emergency exception, § 24-410(c)
Rule 2/4 · Analysis 2.5/4
Issue 3
Substantial completion and remedies
Rule 1/4 · Analysis 1.5/4
The submitted answer (what the grader saw)
MEMORANDUM

TO: Dana Marberly
FROM: Examinee
RE: Solano v. Varkell Roofing LLC

I. Right to Cancel

Under the Home Improvement Contracts Act, Wakanoke Rev. Code section 24-410, every home improvement contract over $2,500 must be in writing and must state the total price, a start date, and an estimated completion date. The Varkell contract states the price but paragraph 7 says only that work will be scheduled as crew availability and weather permit, with no start or completion date. The contract also contains no notice of the right to cancel and no cancellation form. Where the contractor fails to give the required cancellation notice, the cancellation window does not begin to run, so Ms. Solano's right to cancel remained open when she told Reyes on July 2 that she wanted to stop the project.

Varkell will argue the emergency exemption applies because the April 4 tarp work was emergency work. That argument likely fails as to the April 6 full replacement contract: the emergency was over once the tarp was installed, and the replacement of the entire roof system including the garage and gutters is not emergency work. The pre-checked waiver checkbox in paragraph 12 is also likely ineffective, because a consumer cannot waive rights under the Act and a pre-checked box is not a knowing waiver.

II. Recovery

If cancellation is effective, Ms. Solano can seek restitution of the $9,200 she has paid. Varkell may assert an offset for the value of work performed, and the court may consider that the main house roof was completed. The substantial performance argument in Reyes's email goes to damages, not to the statutory cancellation right. Because the Act provides for attorney fees to a prevailing homeowner, fees are likely available.

III. Conclusion

Ms. Solano likely retains a statutory right to cancel because the contract omitted required terms and the cancellation notice, and the emergency exemption likely does not cover the April 6 replacement contract. She has a strong claim to recover her payments, subject to a possible offset.
Full evaluation, verbatim

LAYER 1 — ISSUE COVERAGE

Issue 1 — Applicability of the Act; violations of §§ 24-410(a) and (b) · Rule 3/4 · Analysis 3/4 → 3.0

  • Credit: You correctly identify that the writing must state price, start date, and completion date, and you correctly flag that "paragraph 7 says only that work will be scheduled as crew availability and weather permit, with no start or completion date" — that's the (a) violation nailed with the right fact.
  • Credit: You correctly note "the contract also contains no notice of the right to cancel and no cancellation form" and conclude the cancellation window "remained open" — the right result under (b).
  • Deduction: You never explicitly clear the $2,500 threshold against the $18,400 contract price — an easy point the point sheet expects be stated, not just assumed.
  • Deduction: You don't state the specific mechanics of the (b) notice (separate document, delivered at signing, 3-business-day window), so the rule is functionally implied rather than fully articulated.

Issue 2 — Emergency exception, § 24-410(c) · Rule 2/4 · Analysis 2.5/4 → 2.25

  • Credit: You reach the correct conclusion that "the replacement of the entire roof system including the garage and gutters is not emergency work," which tracks Petrakis's holding that an emergency component doesn't sweep in the whole contract.
  • Deduction: You never cite or state the Petrakis three-part test (separate document, signed before the emergency work begins, specific to the emergency and the work). Instead you substitute a generic consumer-protection theory — "a consumer cannot waive rights under the Act and a pre-checked box is not a knowing waiver" — which is not the rule the Library actually supplies, and misses that the waiver independently fails because it was inside the main contract and signed after the tarp work.
  • This is a rule-statement gap that also weakens the analysis, since the timing failure (waiver came after the emergency, not before) is never surfaced.

Issue 3 — Substantial completion and remedies · Rule 1/4 · Analysis 1.5/4 → 1.25

  • Deduction: You never mention Danvers, "substantial completion," or the "whole of the work promised" standard. This is the point sheet's central tension, and it's essentially skipped — you assert the cancellation right "remained open" (in Issue 1) without ever testing whether substantial completion has since occurred.
  • Deduction: The facts that drive this issue — garage roof (25% of area) unstarted, gutters/drip edge not installed, final inspection not done — are never used. Your only completion-related comment, "the court may consider that the main house roof was completed," appears under Recovery as an offset point, not as the Varkell-side argument in a substantial-completion analysis, so the expected tension is never engaged.
  • Credit: You do address recovery of the $9,200 and note fees are "likely available."
  • Deduction: You never state the willfulness standard ("knew or should have known") that gates fee recovery under (d), so the fee conclusion is asserted rather than supported.

Issue total: 6.5/12

LAYER 2 — STRUCTURAL RUBRIC

  • Rule articulation: 2/4 — solid on (a)/(b), thin on (c) (wrong theory substituted for Petrakis), essentially absent on Danvers/willfulness.
  • Fact-to-rule application: 2/4 — good on ¶7 and notice facts; garage/gutters/inspection facts never tied to substantial completion.
  • Organization & instruction-following: 4/4 — proper memo format, headings used, no separate facts section, facts woven into analysis as instructed.
  • Audience & tone: 4/4 — candid, appropriately internal register for a partner memo.
  • Issue coverage: 2/4 — Issues 1–2 substantially covered; Issue 3's core tension is largely missing.
  • Red herrings: The failure-to-read, "#1 rated" advertising, and neighbor-noise red herrings are silently omitted — acceptable, no deduction, no bonus.

Organization/tone deduction: none warranted (document type, headings, and register all comply).

OVERALL This is a passing-level answer on the notice/waiver issues but it never engages the substantial-completion analysis that the point sheet treats as the case's central factual dispute, which caps its overall strength.

Highest-leverage fix: Add explicit Danvers-based analysis comparing Varkell's best argument (main-house roof water-tight and in use) against Solano's better facts (unstarted garage section, missing gutters/drip edge, no final inspection) to reach a reasoned conclusion on whether substantial completion has occurred — this is the single gap costing you the most credit.

This entire evaluation was generated in about two minutes.

Get yours — first one's free →Google sign-in · no card

Educational feedback against our rubric — not legal advice and not a prediction of bar exam results.